Canadian Log Homes by Kodiak Log Homes.
Log Homes Site Map
Canadian Log Homes by Kodiak Log Homes

NEW FEATURE:
From The Ground Up
Follow a log home under construction

 

Home

Construction:

  • Constructing Log Homes
  • Styles of Log Homes
  • Features for Log Homes

  • . . . .Log Spiral Staircases

    Packages:
  • Log Homes Packages
  • Windows/Doors for Log Homes
  • Roof Systems for Log Homes


  • Design Services:
  • Log Home Plans
  • Log Home Design


  • Photos of Log Homes:
  • Our Log Home Yard
  • Pictures of Log Homes


  • Other Info:
  • Log Home FAQ
  • Testimonials
  • Request Info
  • Contact Us
  • Log Home Resources


  • Log Home Dealers Wanted!



    Site Map


    Visit Kodiak Log Homes:
    Log Home Shows
    Email Kodiak Log Homes at:
    sales@kodiakloghomes.com

    International Log Builders Association

    Member of the International Log Builder's Association

    The Wang's

    Setup Day!!!!

    The setup of the Wang's home took 3 days, with 4 to 5 builders working dawn to dusk. The crane operator was one of the best that we have worked with, and this fact enabled us to complete the setup in record time.

    --------------- DAY 1 -----------------

    The 70 ton crane arrives at 7:30 AM to get into position. The first log is set on the wang's utility building. One of our builders working the truck  ... locating and hooking the logs for the next set.
    The first round is complete on the utility building. The fourth round is being set on the utility building. The builders discuss the logs to be placed next.
    Each log is tapped into place in the corners to set the logs tightly together. The first round is placed on the Wang's main house. The setup of the utility building is completed by noon.  The setting of the first round on the main house is being set.

    --------------- DAY 2 -----------------

    The utility building has had the scrapes and marks touched up. The framers have already been hard at work framing the interior partition walls. A beautifull bright day makes this image look a bit dark.  Work is proceeding well on the setup of the main house. A beautifull bright day makes this image look a bit dark.  Work is proceeding well on the setup of the main house.
    Working the truck.  The chains that secure the mid point of the stakes are removed. The setup continues to go exceptionally well.  Here we are setting some of the interior log walls. The setup continues to go exceptionally well.  Here we are setting some of the interior log walls.
    The setup continues to go exceptionally well.  We are now drawing to the end of the second day. The setup continues to go exceptionally well.  We are now drawing to the end of the second day.

    --------------- DAY 3 -----------------

    The start of the final day of the Wang setup. At the start of the third day, we have all of the walls set up to the point where the door and window headers will be the first logs to be set. This picture shows a nice perspective on the framing of the interior walls of the utility building.
    The setup of the Wang's log home shell is complete. The setup of the Wang's log home shell is complete. The setup of the Wang's log home shell is complete.
    The setup of the Wang's log home shell is complete.  This shot shows one of the log archways. The setup of the Wang's log home shell is complete.  This shot shows one of the archways and some of the wall slots that have been cut to receive the drywall cladding of a framed partition wall. The setup of the Wang's log home shell is complete.
    The setup of the Wang's log home shell is complete. The setup of the Wang's log home shell is complete. The setup of the Wang's log home shell is complete.